Planning Creative Capacity Across High-Volume Editorial Brands
Creating earlier demand visibility and supporting more deliberate designer allocation across Healthgrades and Medical News Today.
Challenge: High publishing volume generated more potential demand for custom creative support than the studio could address reactively.
My role: I improved the visibility of Creative Studio work within an existing priority asset tracker and helped connect editorial planning with designer capacity.
Outcome: The studio gained earlier visibility into dozens of priority assets each month, enabling more deliberate assignment planning and reducing some last-minute surprises.
By the Numbers
Approximately 400 articles published by Medical News Today each month
Dozens of priority assets represented in monthly planning
Approximately 30–70 priority items during a typical publishing cycle
Multiple editorial, design, illustration, photography, SEO, and content-operations contributors
One shared constraint: custom creative demand exceeded available capacity
The Operating Challenge
Healthgrades and Medical News Today operated within different editorial models, but both required Creative Studio support in high-volume publishing environments.
Medical News Today alone published approximately 400 articles per month. At that scale, not every article could receive the same level of custom illustration, design, or photography.
Creative teams needed earlier visibility into:
Which content was being prioritized
What type of creative support was required
When assets were expected to publish
Which designers would be needed
Where multiple requests competed for the same capacity
Without that visibility, assignments could become reactive and difficult to balance across the studio.
The challenge was understanding upcoming demand early enough to make responsible allocation decisions.
My Contribution
For Healthgrades, I improved an existing priority asset tracker and entered Creative Studio projects into the shared planning view.
I did not create the tracker or own the full process. My responsibility was to ensure that creative work was represented accurately so editorial and creative stakeholders could plan from the same information.
That distinction mattered. Editorial teams had visibility into their priority content, while the Creative Studio needed visibility into the production effort those priorities created.
My contribution connected those two views.
What I Changed
Incorporated creative work into editorial planning
I added and maintained Creative Studio project information, including:
Upcoming asset needs
Publication timing
Assignment status
Creative ownership
Open questions
Potential timing conflicts
This reduced the separation between editorial planning and creative production.
Created earlier demand visibility
By seeing upcoming work sooner, the Creative Studio could assess:
How many designers might be needed
Which skill sets the work required
Where demand was concentrated
Which assignments should be redistributed
Whether the expected volume was realistic
The tracker did not eliminate changing priorities or urgent requests. It did give the team more time to prepare for them.
Supported better designer allocation
The studio could review the upcoming body of work instead of assigning projects one request at a time.
Assignments could be considered against:
Designer workload
Available capacity
Required creative skills
Publication timing
Competing priority assets
The tracker’s clearest value was helping the creative team understand what was coming and allocate resources more deliberately.
Created a shared planning reference
The tracker gave editorial and Creative Studio stakeholders a common point of reference for conversations about:
Upcoming deadlines
Required deliverables
Assignment status
Open questions
Production conflicts
Timing or scope changes
Rather than relying entirely on individual conversations or separate team plans, stakeholders could work from a more consistent view of the upcoming portfolio.
The Result
The improved planning process helped:
Give Creative Studio earlier visibility into priority editorial work
Incorporate creative projects into a shared cross-functional view
Support planning across dozens of assets each month
Improve the allocation of designers
Identify workload conflicts sooner
Reduce some last-minute surprises
Strengthen coordination between editorial and creative teams
The most significant outcome was a more informed way to plan limited creative capacity within a high-volume publishing environment.